Please be advised of the following, as approved by the CDC Environmental Health Officer:
Date | Out of Hours Work | Construction Actions | Number of Workers | Road Sweeper Required |
---|---|---|---|---|
Saturday 01/03 | 1.00pm-4.00pm | Installation of three foundations within the logistic road Installation of beam, removal of 2 beams | 3 6 | Yes |
Sunday 02/03 | 8.00am-5.00pm | No | ||
Saturday 08/03 | 1.00pm-5.00pm | Remove the internal wall in line with link bridge Installation of 2 braces Installation of 3 columns and removal of beams | 3 4 3 | No |
Sunday 09/03 | 8.00am-5.00pm | Yes | ||
Saturday 15/03 | 1.00pm-5.00pm | Installation of 2 braces | 4 | No |
Sunday 16/03 | 8.00am-5.00pm | No | ||
Saturday 22/03 | 1.00pm-5.00pm | Installation of 2 braces | 4 | No |
Sunday 23/03 | 8.00am-5.00pm | No | ||
Saturday 29/03 | 1.00pm-5.00pm | Installation of 2 braces | 4 | No |
Sunday 30/03 | 8.00am-5.00pm | No | ||
Saturday 05/04 | 1.00pm-5.00pm | Construction of 2 crash decks Installation of 2 braces | 3 4 | No |
Sunday 06/04 | 8.00am-5.00pm | No |
We can confirm that there are no deliveries to the Site outside of existing agreed working hours.