Please be advised of the following, as approved by the CDC Environmental Health Officer:
Location of works planned:
- Works are only occurring on the existing plant at the Home of Rolls-Royce, with equipment arriving externally through the logistics road.
Works required:
- Connection of sprinklers and gas systems enabling production to resume on 22nd April.
Vehicles, machinery and personnel:
- Two or three vans, three electric lifting platforms, six workers and an internal road sweeper.
Disruption:
- Instalment makes little noise and is within the existing plant (1), the road sweeper will be kept on site and only used if required.
Additional Hours:
Date | Hours | Number of Workers |
---|---|---|
Monday 21/04 | 8.00am – 5.00pm | 6 |